20 October 2021
The NSW Land and Environment Court (Court) has rejected a challenge to the approval of Santos’ Narrabri Gas Project (Project). [1] The decision develops the law on the assessment and conditioning of Scope 3 or ‘downstream’ greenhouse gas (GHG) emissions and clarifies the requirements for cumulative environmental impact assessments.
The Independent Planning Commission (IPC) approved the Project on 30 September 2020, following an extensive environmental assessment process involving a record 23,000 submissions received during the public consultation period and an unprecedented seven-day public hearing.
The applicant, a community action group, challenged the IPC’s approval of the Project on four grounds, three of which concerned the IPC’s consideration of the projected GHG emissions of the Project. The fourth concerned the cumulative environmental impacts of a transmission pipeline, that would be required to convey gas from the Project to the domestic market, but did not form part of the Project application.
Although the applicant was unsuccessful in each of its arguments, the Court’s decision clarifies the approach to the assessment and conditioning of Scope 3 GHG emissions, insofar as Preston CJ found that:
Concerning cumulative impacts, the Court clarified the circumstances in which two projects are sufficiently related to one another such that the assessment of one project requires consideration of the environmental impacts caused by the other.
The Court found that in circumstances where the Project would connect into one of two transmission pipeline options that were as-yet imprecisely defined, and given the disconnection between the impacts of the Project and a linear infrastructure project hundreds of kilometres away, it was appropriate not to have considered the potential environmental impacts of the pipelines when assessing the Project.
The decision is relevant for fossil fuel developments and other major projects, particularly as the Court has now clarified that consent authorities must consider whether to impose a condition relating to Scope 3 emissions as part of the assessment and determination of a project.
Further, the decision clarifies the approach to be taken for the assessment of cumulative impacts for major projects, especially projects which rely upon the construction of major linear infrastructure for their operation, such as a gas transmission pipeline or electricity powerlines.
In relation to GHG emissions, the Court made several findings that have general application for future fossil fuel projects, including that:
In relation to cumulative impacts, the applicant argued that the IPC had failed to consider the environmental impacts of the construction of a proposed transmission pipeline that would transport the gas extracted at Narrabri to the domestic market. At the time consent was granted for the Project, the proponent was considering two potential options for the major pipeline route but a final decision about the preferred pipeline had not yet been made. The Project application did not assess the impacts of either option.
In light of this, the IPC imposed a condition of consent preventing the proponent from commencing Phase 2 of the Project (gas production) until planning approval had been obtained for the potential pipeline.
In dismissing the applicant’s arguments on this ground, the Court held that the likely impacts of a gas transmission pipeline were not ‘likely impacts’ of the Project that was the subject of the development application (and therefore the environmental impacts of the potential pipeline did not need to be considered as part of the Project assessment) because:
Proponents of fossil fuel developments and other major projects, including those that are to be developed concurrently with linear infrastructure projects, should be aware of the implications of this decision.
Steps can be taken to improve a project’s environmental assessment in line with the reasoning in this case. This includes:
[1] Mullaley Gas and Pipeline Accord Inc v Santos NSW (Eastern) Pty Ltd [2021] NSWLEC 110.
Authors
Head of Environment and Planning
Special Counsel
Senior Associate
Tags
This publication is introductory in nature. Its content is current at the date of publication. It does not constitute legal advice and should not be relied upon as such. You should always obtain legal advice based on your specific circumstances before taking any action relating to matters covered by this publication. Some information may have been obtained from external sources, and we cannot guarantee the accuracy or currency of any such information.
Head of Environment and Planning